Run MRP on one plant and purchasing from another plant

0 Kudos

Dear Experts,

My requirement is I wanted to purchase material from PR generated by MRP but I am not able to create PR as I wanted. Here is my scenario.

Process MTO

Sales requirements & MRP run on plant A

Procurement from plant B

I have used special proc key 70 for material and plant A still my PR is generating on plant A.

Kindly provide resolution.

Thanks in advance

Lakshmipathi
Active Contributor
0 Kudos

You already posted the query with this primary tag and again cross posting with different tag here which would be removed as it is discouraged as per SCN RoE. Please refrain doing this.

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You need to define in plant A a special procurement with stock transfer, where plant B is the supplier.

MRP will generate a stock transfer from plant B to plant A and the stock transfer requirement will generate a requisition in plant B.

Regards,
Caetano

0 Kudos

Thanks Caetano.

But that is not my actual process. We are capturing sales requirement on plant A but plant B is purchasing material form vendor and transferring to plant A.

As you suggest, my purpose will not get satisfy.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Mannu

I'm afraid there is no standard solution for this issue. You can try to implement a BAdI in MRP to change the requisitions and solve this issue, but you may face issues in MRP net requirements calculation. See below the BAdIs available for MRP:

https://blogs.sap.com/2013/08/12/badis-for-mrp/

Regards,

Caetano