Hi All,

When i am doing PGI with Movement type 281 Q and after checking my reports ,the actual costs are showing against the WBSE not against the Network Activity.

Please advice me is there any setting to do this so that after doing PGI i will should get the costs against the Network Activity.

Regards

Firdosi

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jul 30, 2008 at 05:57 AM

    Hi,

    Check the profile of Parameter for network,(OPUV) . There u must have missed to tick Activity account assign.

    Regards

    N.Raju