Former Member
Jul 25, 2008 at 07:17 PM

Restrict purch reqrel at Plant- Mfg Plant

18 Views

Hi,

I have a scenario to take care of distribution demand at plant to take care of transportation arrangement for 2 days. i.e. Plant needs 2 days to arrange for the trucks.

In given setting we have maintained stock transfer horizon at DC. Given case is if you maintain Stock transfer horizon at DC as 4 days, now if you have forecast coming on the 5th day and also the transportation time between the DC and Plant is 5 days in that case the distribution demand at the plant will come on the 1st day i.e. Today. We cant ship the material today, since we require 2 days of Lead time to arrange for the truck.

Tried with GI time, Stock transfer horizon in Plants but didnt work out. Can any one guide me with the settings .

Thanks and Reg

Jignesh