Hi ,
We are facing a issue of Open Purchase orders not appeared in Stock requirements list and also it is not considered as requirement for MRP Run against reservation.
As aresult for a reservation demand of 10 units we are ending with Open POs 10 units and a additional planned order 10 units.
Material Type : ERSA
MRP Type : PD (or VB)
Lot size : EX ( HB if MRP Type is VB)
Could you please throw some light to correct our settings to MRP to consider Open POs?
Saravanan
Can you check to see if there is a re-order point set up for this materia? That could be causing the problem too.