Skip to Content

External processing -operational subcontracting

Hi Team,

Need your help on urgent issue.

Requirement:

My client is a one of the automotive cmpy (cars).there will be a four sub processes. Final one will be painting. currently there sending cars to vendor for painting work and get the finished cars. Vendor is charging based on painting services.How to configure this in the system. Please help on this issue. Need E2E solution.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Mar 01 at 10:06 AM

    Hi,

    Hope you are working on ECC R/3.

    Kindly check the below Link.

    https://blogs.sap.com/2013/11/26/subcontracting-process-in-production/

    Thanks

    Kumar

    Add comment
    10|10000 characters needed characters exceeded