cancel
Showing results for 
Search instead for 
Did you mean: 

Target costs in variance calculation.

Former Member
0 Kudos

Gurus,

I have a problem that in KSS1 when i am doing variance calculation for a cost centre, the target cost is generated but when i remove test run, this cost is not getting passed to the order. i.e i cannot see this in kks2 which is the variance calculation for the order. My ultimate aim is to view the target costs in the production order. Please help with this issue.

Thanks in advance,

Anand Deshmukh.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

resolved

Former Member
0 Kudos

Hi,

Please go to COR3. Enter the Process Order Number. Now in Menu Go to > Cost > Analysis. You may see the Target Cost for the order.

Regards,

Jigar

Former Member
0 Kudos

Sir,

I am talking about production order, not process order. And i know that the costs can be viewed in the order. My problem is that it is displaying 0 costs in the order. since the variance calculation is not passing the costs to the order hence it is not displaying in the order.

Thanks.

Former Member
0 Kudos

Hi Anand,

Please try the following T Code.

KKF4 - Create/Change Plan Costs

Regards,

Jigar