I am issuing components from Production Warehouse against production order, stock lies at RM warehouse. Now, for various planned orders i will transfer components from RM to PR warehouse but there could be some stock already in PR warehouse so the system should subtract the available quantity and give a net requirement to be transferred from RM to PR.

(NOTE: this is before conversion of Planned Ord to Prod Ord)

Kindly help.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Mar 04 at 04:52 PM

    Hello

    The best way to do it is using transaction MF60 to transfer your components to the PR storage location.

    See this blog for details:

    https://blogs.sap.com/2015/02/25/pull-list-and-stock-determination-in-production/

    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 06 at 04:34 AM

    Thanks Sir,

    I followed your link for stock determination But when i did MF60 not displayed anything even when i enter plannned order number got error "no order exist"

    please revert me where I made mistake.

    Thanks & best regards.

    salahuddin

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 06 at 01:06 PM

    Hi Sir,

    It's very helpful answer, thank you so much. actually I didn't enter my production storage location in Stock determination item table( t code OSPX)

    Best Regards.

    Salahuddin

    Add comment