Hello SAP supremes.

There is a prod order for mat1 (header ) for 100 qty.

in this there is scrap for 20% .

the Qty delivered is 80 .

Now if I go to Migo it should not let me recieve any more qty but the delivery competion indicator does not come.

Why is not completing the delvery considering the scrap.

Should i do a seperate transaction to adjust scrap.?

Thanks

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Jul 25, 2008 at 05:57 AM

    hai,

    Did u mention the scrap % in BOM of Production order.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 25, 2008 at 06:19 AM

    Hi Friend,

    Please use MR22 to scrap any quantity for that material.

    Regards

    Krishnendu

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 25, 2008 at 07:06 AM

    Hi KK,

    if u are expecting delivery of only 80 why are u giving the qty as 100. U create the production order for 80 and then mention the scrap qty in BOM

    Hope this resolves ur problem.

    award points if found useful

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.