hi,

on the PRT availability check, system shows the msg.,

"PRT availability could not be checked"

so which control parameters are needful?

Edited by: vijaysinh patil on Jul 25, 2008 7:28 AM

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jul 25, 2008 at 05:31 AM

    Hi,

    Production Resource/Tool (PRT) Availability Check

    Use

    What is Checked?

    A status in the master record of every PRT category (material, PRT (misc.), document or equipment) determines whether a PRT is available or not. During the availability check the system statically checks this status to see whether the PRT is available for use or not.

    The availability check for PRTs does not check whether other orders or networks require the same PRT at the same time.

    In the case of PRTs with material masters, you can also conduct an availability check in the plant stock of the PRT. The system then check in the following stocks:

    Unrestricted-use stock

    Stock in quality inspection

    Unrestricted-use consignment stock

    Consignment stock in quality inspection

    You specify in Customizing, whether the system only checks the status or whether it checks the status and the plant stock.

    When is Availability Checked?

    The availability check takes place either automatically or when you start it manually.

    You can specify in Customizing whether the system should automatically check material availability and when to run this check . For example, the availability check can take place when you create or release a network.

    You can manually start the availability check at any time. In network maintenance choose Edit ® Availability ® PRT.

    Hope this helps.

    Reward if useful.

    Regards,

    Tejas

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 25, 2008 at 05:36 AM

    Hi,

    Check in OPJK - Checking Control. Select your plant & Order type.

    Select business function 1 for PRT Availability check at Order creation & 2 for when order release.

    In this check PRT availability check field.

    Remove tick mark from - No check.

    Checking rule - PP

    PRT release - User decides

    Regards,

    Dharma

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 25, 2008 at 05:51 AM

    Hi vijaysinh,

    Check whethere you have assigned PRT in routing for that particular order . If you havent assigned it system cant check availability for it .

    Revert back

    Neal

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 25, 2008 at 05:55 AM

    Hello Vijaysinh Patil,

    In the configuration availability check rule for a particular order type,

    (SPRO->Production planning->shop floor control-->availability check) In OPJK maintain checking control for your Plant and order Type

    Their you have select the availability check for PTR and select the automatic availability check when production order release/save.

    U have to assign the correct formula for PRT.

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 25, 2008 at 05:57 AM

    hi,

    if u want to make compulsion availability check for PRT then try this t code-OPJK. (at the time of order creation) .tick PRT check.

    manish

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 25, 2008 at 08:25 AM

    Hi Vijaysinh,

    Check following nodes are configured in u r system

    These are avaliable in PP as well as in PM.

    Availability Check for Material, PRTs and Capacities

    Define Checking Rules

    Define Scope of Check

    Define Inspection Control

    Ramesh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.