CK11N : No price could be determined for Internal activies

Former Member
0 Kudos

Dear all,

While running the Ck11n, the Internal activity prices are not calculating.

I have done Kp26 properly for the period 12, 2017. And in Valuation variant also selected Plan price for the period.

Activity types and cost centers also correctly assigned in the Work center.

Please help.

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi,

Did you mark the reference indicator for the activities you assigned in the costing tab of work center master? You can also check what your formulas are for the activities and see if a value is entered in the necessary areas like setup, machine or labor time in the routing of the material.