I need to make changes in a number of resource in APO at a time. Do we have a mass maintenance process in APO to do that. I need to be able to chnge the Capacity Variants.

Is there a way if i can put that in a batch job in the background.

Reply awaited.. thanks in advance.

Regards,

Manoj

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

use MASSD for maintining resources

use MASSBACK for doing background maintainance

edit: oops looks like i double posted.

a having problems with SDN forum while posting.. is it just me or any of you have issues?

Edited by: Harish AN on Jul 25, 2008 12:00 PM

Former Member
0 Kudos

Thank you Harish. I will award points and close the thread.

Regards

Manoj

Answers (1)

Answers (1)

Former Member
0 Kudos

Try MASSD and see if you can pick up your resources and the fields to be changed