Hi,

While creating contract in periodic billing with rental contract, I get an error tht " Plant XYZ is not assigned to controlling area".

How to resolve it ? And why it is asking for controlling area?

Plz suggest.

Regards,

Ankur

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

You need to create a controlling area and assign it to the company code. I don't think you can assign a controlling area drecty to a plant. As the rent is considers as cost, the controlling area is required.

SPRO --> Controlling --> General controlling --> Controlling Area --> Define controlling area.

There is another option to assign the controlling area to company code, make that setting too.