on 07-24-2008 5:03 PM
HI Experts,
I need to get the working days in plant_1000.
I know there is a FM regarding this, its DATE_CONVERT_TO_FACTORYDATE.
but, i dont think that will help much to me, to meet my requitement.
my requitrement is,
I need to subtract the MARC-WEBAZ(Days required for processing the Goods receipt, their values looks like 1, 2, 3 etc) from a date, say 20080701.
Say, 20080701 - 1 day(=MARC-WEBAZ) = here, I need to get the NEXT WOTKING DAY for plant_1000.
So,
1 - really, Is this FM DATE_CONVERT_TO_FACTORYDATE - helps to me to meet my requirement?
2- if it is not helps much, Wht wuld b the logic in brief to get my requitemt?
3 - Is there any good FM to get it directly?
thanq
Check your factory calendar attched to the plant/Shipping point via transaction "SCAL" or sca2 or sca3
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try using END_TIME_DETERMINE funtion module.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.