Factory Calender - Next Working Day??

Former Member
0 Kudos

HI Experts,

I need to get the working days in plant_1000.

I know there is a FM regarding this, its DATE_CONVERT_TO_FACTORYDATE.

but, i dont think that will help much to me, to meet my requitement.

my requitrement is,

I need to subtract the MARC-WEBAZ(Days required for processing the Goods receipt, their values looks like 1, 2, 3 etc) from a date, say 20080701.

Say, 20080701 - 1 day(=MARC-WEBAZ) = here, I need to get the NEXT WOTKING DAY for plant_1000.

So,

1 - really, Is this FM DATE_CONVERT_TO_FACTORYDATE - helps to me to meet my requirement?

2- if it is not helps much, Wht wuld b the logic in brief to get my requitemt?

3 - Is there any good FM to get it directly?

thanq

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Check your factory calendar attched to the plant/Shipping point via transaction "SCAL" or sca2 or sca3

Answers (1)

Answers (1)

Former Member
0 Kudos

Try using END_TIME_DETERMINE funtion module.