Gantt Chart - ONLY Critical path activity Display

Mar 01 at 06:05 PM


avatar image

Dear experts,

I am in need of displaying Activities that are ONLY on Critical path in CJ2B Or any other transaction that will let me do this.

Q: Is there any configuration / Settings options which I can do similar to MS Project - Gantt chart (attached) so as to Display activities that are on 'Critical path' only.

Note: I have checked most of Configuration (Project Planning Board), Highlight objects, Settings - Options. but couldn't find any. Please suggest.

I have also referred to few OSS notes, where I couldn't find required information. (Ex: 500933 - Proj.plng board: Recomm., additional information, consulting)


10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Ken Melching
Mar 02 at 01:08 PM

There is a much better looking Gantt chart in PSHLP, PS Handling Large Projects. You need to activate HLP first, then use transaction PSHLP20. Although it does not have the same functionality as Planning Board.

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Thanks Ken for your suggestion. However, we aint using PSHLP. Will keep this in mind when the need arises.

Could you Please tell if activity description can be displayed above Activity bar in CJ2B?. Also, I thought the 'Basic Start and Basic Finish' can be displayed on the bar (Basic dates). These 2- functionalities I am checking if possible in CJ2B.


sdn sap Mar 02 at 06:37 AM

Dear All, Found the answer. We can select 'Basic Total Float' value under 'Filter - Define and Apply' option in CJ2B screen (Toolbar in 2nd row). Basic total float value '0' will display ONLY Critical path activities.

Hope this helps others as needed.