Planning startegy 30

Hi all ,

I am using the planning strategy 30, Here i created many sales order wioth different delivery date but the system creates only one planned order for all these sales order , I want one planned order for one sales order ,

I have used the availability check 01, and individual collective requirements 1,

Please give me solution.

Best Regards,

Kumar

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Jul 24, 2008 at 07:56 AM

    Hi,

    Planning Strategy 30 is not a MTO Strategy.

    With this Strategy, system will not create the Proposals individually.

    It will club together the requireents per day and propose a single receipt eleemnt.

    This can only possible with MTO Scenarios.

    Lot Size: EX and Ind/Collect indicator 1 will not help..

    Regards,

    Siva

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Kumar,

      With strategy 30 you can work with PIRs (demand without reference to customers) as well as with sales orders (customer requirements). Here sales orders will not consume your PIRS and you can perform planning annd production in parallel to both PIRs and Sales orders.Example retail industry.

      I thinkyour doubt is clear that you can use DM in strategy 30. Production by lot means you can carry out the production for independnet lot sizes for both PIRs and individual sales orders.

      Any question then please write with rewarding the suitable points.

      Regards,

      R.Brahmankar

  • Posted on Jul 24, 2008 at 07:44 AM

    Hi,

    Please check the individual/collective indicator in material master MRP3 view, set it to the individual requirement.

    What is your MRP type and lot size?

    Regards,

    R.Brahmankar

    Edited by: R Brahmankar on Jul 24, 2008 1:16 PM

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 24, 2008 at 09:54 AM

    hi,

    for ur strategy 30 ,it means ur planning for month of different customres , in this case u will get one planned order, if ur planning for next month then it will creat new planned order.

    manish

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.