Dear all.

PO rate: 159.00 [Not changed since PO creation]

GR done in June having GR/IR = according to 162.64

In table MBEWH

Year Period MAP

2009 01 159.00

2009 02 159.00

2009 03 162.64

For current period [04/2009] MAP = 146.87

My question is:

1. Why GR made in June having GR/IR posting according to 162.64, but GR is valuated by PO Price only??

2. If GR is done today, which price will it take up, either 159.00 [PO Price] or 146.87 [Current MAP]

While posting MIRO for GR made in June, GR/IR = according to 162.45 is coming in simulation. But in amount field it is according to 159.00. So unable to post MIRO

Pls suggest on priority

Tushar