Can any one explain the flow for Customer supplied material

for processing labour charges only.

How can i start the inward material, and return it with billing.

Thanks & Regards

Yogesh

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jul 23, 2008 at 12:32 PM

    Dear Yogesh

    - Create the material (say M1) in receiving plant with material type UNBW.

    - While doing MIGO, only stock quantity getting inwarded without any values

    - Create M1A as HALB

    - Create a BOM in CS01 for M1, keeping M1 material as the header component and M1A as component

    - Confirm the service by one operation with material code M1A (material type HALB) through MFBF

    - While doing PGI, stock at servicing plant will get reduced.

    - HALB being sent to Customer with no ED, Cess, Tax etc.

    - Raise an invoice (charging ONLY for service charges)

    - TDS applicable

    thanks

    G. Lakshmipathi

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.