hello all
I am relatively new in KANBAN so I need the experts help.
we created a new replenishment strategy type for external procurement in Kanban, with summarized JIT calls.
according to sap.help.com, we set up a scheduling agreement.
the material is not MRP relevant, the storage location is excluded from MRP but when we create a control cycle, the newly created strategy does not appear in the list of external procurement.
can you help me understand what I might be missing?
thank you all
we found the reason: although all the forums claim that the MRP indicator for Sloc in MRP4 should be set on 1, it has in fact to be empty
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi allwynrajkumar
read the answer.
the MRP indicator for Sloc in MRP4 should be empty and not 1
no experts?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.