on 07-23-2008 9:35 AM
I am tryinmg to make posting date to be system date for completion confirmation. How can I achieve this ?
Regards,
VM
Hi All,
Request:
"I am preparing functional specifications for a report. The confirmation date should be the system date when the user confirms the order."
In table AFRU, field BUDAT is the "posting date" but this is open for edit.
Field ERSDA is the system date for the confirmation and cannot be edited.
So the FS should be to use AFRU-ERSDA.
Hope it helps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can set (or logically it is by default setted) in the system under PM Order/notification confirmation node in PM/CS Services.
If u want to retrive information which are t tables.
Following is the logical path
AFRV,AFVC,AFVU,AFVV,AUFK may help u.
Ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
VM,
Can you be more specific?
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.