Dear All,

While creating a Workcenter with CNR1, in the Costing field it is showing error Activity Type is not assigned to Cost Center. When that is being done through transaction KP26 it is throwing error that 'P' rate type to be maintained in system settings.The present rate type setting is with 'M'. If I change it to 'P' in transaction OPSB, what will be its financial implications. Is it right to do so?

It is the new work center what I am creating for a different company code of ours with different Plant and Business Area.

Points will be awarded..

MRD

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

As you are telling, its for different Co Code, plant as such.

Why dont you create a new Actvity type in KLO1 and mention the rate as required in KP26 and assign it to the Cost center for your work center.

Regards