How to MRP Setup

Former Member
0 Kudos

Dear All

I'm intending setup MRP for system,

Could you please explain me about MRP profile, MRP group, MRP controller, MRP type ?

Do you have any document about setup MRP ?

Thank and Best regards,

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

MRP Profile -All the MRP 1,2,3,4 views in the material master data are entered in this profile and create MRP profile.

When you are creating Material Master in MM01 while entering the plant and storage location enter your MRP profile so that you do not need to enter the MRP data again

MRP Group: You can create the MRP Group so that material can be tracked.

Setting --> SPRO-MM-Consumption based planning -MRP Group

MRP controllers : Setting --> SPRO-MM-Consumption based planning -Master data -Define MRP group.

MRP types : Setting --> SPRO-MM-Consumption based planning -Master data -Define MRP types

G.Ganesh Kumar

.

Former Member
0 Kudos

Hi

Thank for your answer.

Could you please tell me what are MRP group, MRP Controller, MRP Type ? and purpose of setup them?

Thanks and Best regards,

Former Member
0 Kudos

Hi,

MRP Group: MRP group is a planning stragegy for carrying out the MRP

In this group there are two types from procurement side

1 ) MADE TO ORDER

In this once sales order is booked ,MRP will run and the P.R will be converted to P.O .

2) MADE TO STOCK: Depends on the forecast model they will plan material and keep the finished product in STOCK

MRP CONTROLLERS: It is like a production controller in an industry . He will plan all the required material for the daily plan.

It will be classified according to the materials & Buyer like

Casting - one MRP controller

Forging -One MRP controller

All Bought Ourt -One MRP controller

Sheet Metal -One MRP controller

*MRP TYPES In the MRP types different categories are there

1: Produce to Demand

2 Consumption based planning

3 Forecast based planning

G.Ganesh Kumar

kunal_ingale
Active Contributor
0 Kudos

HI

MRP groups are used when the plant division for planning is not enough for the division of the different materials MRP requirements. You assign different groups according to the requirements to run MRP (different Settings). These settings will be taken in account when you run MRP for single item or total planning.

MRP controller is the person in charge of the MRP run for the materials. It is still a further division on your MRP. This is work load related. You can have one MRP controller for materials with different MRP groups.

On your MRP group, you will define the parameters for the MRP run. These parameters are calculated in accordance with the settings on your material master MRP views.

Available stock =

Plant stock - safety stock +

receipts of (purchasing orders + purchasing

agreements + production orders) - required quantity.

This means that all the requirements are calculated in the bases of your material master settings and your MRP group settings.

MRP TYPE

It is procedure that you set in the system on how the

Material is planned

Reorder Point

Seasonal requirement

Replenishment

Vendor Managed

Forecast Based

Master production Scheduling

REGARDS