PP order date issue

Hi PP Gurus,

Iam creating production order via T-code CO01 and have 3 operation in the production order. In the routing the leadtimes in maintained for each operation like 15 days.The schedule type is forward scheduling.

When i create production order the order scheduled date is calculating accroding to the lead time maintained in the routing. But the finish date is always one day difference from the scheduled date.

If i create production via MD04 system will consider the plan in house time in the MRP view 2 and calculate the basic finish date but we are creating manaully.

Pl advice why this one day difference

Thanks in Advance

Kumar

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jul 23, 2008 at 03:47 AM

    Hi,

    Check the finish time of the production order.

    Assume your production finish date is 22.07.2008 in CO01. But in MD04 the requirement date is 23.07.2008. 1 day difference will come. This is not a 24 hours diiference.

    Check the production finish date & time in CO02. Time is near to 24:00. System assume your req date is 23.07.2008 & 00:00 time.

    So it is almost near.

    Regards,

    Dharma

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      The production order scheduled finish date is 28.07.2008 Time is 04:00 and the Basic finish date is 29.07.2008 Time is 00:00.

      These both dates are same.

      Because 28.07.2008 finishing time is 04:00. From 04:00 to 24:00 time is available in 28.07.08. But system can not use this time. If you want to use this time manually you have to adjust capacity by CM21.

      Basic finish date is 29.07.2008 Time 00:00 is equal to 28.07.08 time 24:00

      I hope you understood.

      Regards,

      Dharma

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.