Can any one tell me about scheduling agreement. In procurement

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Thanks A Lot

former_member581212
Active Contributor
0 Kudos

Hi,

Definition

A form of outline purchase agreement under which materials are procured on predetermined dates within a certain time period.

Structure

A scheduling agreement consists of a number of items, for each of which a procurement type is defined. The following procurement types exist:

Standard

Subcontracting

Consignment

Stock transfer

Delivery of the total quantity of material specified in a scheduling agreement item is spread over a certain period in a delivery schedule, consisting of lines indicating the individual quantities with their corresponding planned delivery dates.

For scheduling agreement items involving subcontracting, you can specify the materials or components to be provided to the subcontractor with respect to each scheduled delivery of the ordered item.

Conditions can apply to the entire scheduling agreement. Conditions at item level apply specifically to the material to be supplied in each case.

Scheduling agreement releases (comprising a header and the actual delivery schedule) are issued to the vendor, instructing the latter to effect deliveries of the relevant material on the dates shown.

Costs can be apportioned among various Controlling objects via the account assignment.

Vendors can issue confirmations to the relevant purchasing organization indicating their compliance or non-compliance with scheduled delivery dates.

If you are using scheduling agreements, you can work with or without release documentation. This is controlled via the document type. Working with such documentation affords the advantage that you can display the valid scheduling agreement releases transmitted to a vendor over a certain period whenever necessary.

With release documentation (in the standard system, document type LPA)

The schedule lines in the system have internal character. This means that you can change them in any way you wish. The schedule lines stored in the system are not transmitted to the vendor until you explicitly create a scheduling agreement release (which may take one of two forms: a forecast delivery schedule or a JIT delivery schedule).

The release documentation allows you to display the releases transmitted to a vendor over a certain period in order to establish exactly when you transmitted which information to the vendor.

Without release documentation (in the standard system, document type LP)

The schedule lines immediately have official character, i.e. they are immediately transmitted to the vendor the moment you save them (transmission time-spot 4 for messages). There is no release documentation in this case.

And for more information pls refer to the following link:

http://help.sap.com/saphelp_erp2004/helpdata/EN/75/ee0fa855c811d189900000e8322d00/frameset.htm

Hope it helps......

Regards,

Priyanka.P

AWARD IF HELPFULL

BijayKumarBarik
Active Contributor
0 Kudos

Hi,

Scheduling agreement is a long term purchase agreement, where you will keep issuing the delivery schedules whenever there is a change in requirement or at predetermined time intervals. The delivery schedule can be on hour/daily/weekly/monthly basis. SA is also an agreement with the vendor for the supply of matl, may be a quanity or value. The delivery dates will be maintained in ME38 ref the SA which are called delivery schedules.So you can maintain the delivery schedule and communicate the vendor on Forecase basis or JIT basis. And when you need some more matl then will only create SA deliveries using ME38. The process start with t.codes are,

1.ME11,

2.ME01,(Scheduling agreement Number)

3.ME31,

4.ME38

5.ME35,

5.MB01 w.r.t Scheduling agreement Number( in the place of PO Number)