Hi Gurus,
Am facing an issue with capacity requirements generation on PM orders
-> Operation Control key has Det. Cap Req. ACTIVE
-> Work center is relevant to finite scheduling.
-> OIOI set up with no check on capacity availability.
Even though when creating and releasing PM order i don't get the requirements (..That exist!).
What can i be missing here ?
Will reward,
Cheers,
Olivier