Hi all,

I have the demand in months for five years & once demand came in i take Heuristics to generate the Planned orders.I have a specific requirement for a specific location Heuristic that SNP Heuristic should generate planned orders only in month of January to March for all the five years.

I am using SNP PDS .The PDS do not contain resource.

Can you suggest a good solution for the above?.

thanks

Kumar