How to restrict the GR for Production Order when Goods Issue is not done

Hi Gurus

How to restrict the GR for Production Order when all the required components for production order are not issued with all required quantity. Even for partial issue system should not allow GR with 101. The user status with RMWA, RMWF & CGFB is not working.

Pls suggest best solution.

Abhijit.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jul 22, 2008 at 02:26 PM

    Hi,

    You can club together the GI nad GR at the time of confirmation..

    I.e Backflush for the components and auto GR for the Product.

    So that you can stream line the Process.

    The best Option would be to use the User Exit:

    Enhancement - MBCF0002

    Functional Module - EXIT_SAPMM07M_001

    Include - ZXMBCU02

    Refer below link for further details..

    How to stop the goods receipt before issueing the goods for production orde

    Regards,

    Siva

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      hi Siva

      Thanks. The client wants the control seperately for processes of Confirmation with CO11N, G.Issue with MB1A or MB26 and Prod Ord. GR with MB31 or MIGO or QA32.

      So backflush will not work.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.