on 07-22-2008 4:21 AM
Hi Gurus,
Im performing a downpayment and these are the steps i did
1) F-47 to create a downpayment request
2) F110 to pay the downpayment
3) FB60 to create the invoice
4) F-54 to clear the invoice using the downpayment created
However, after I have done F-54, it says document 400000024 posted. But when I goto FBL1N, this document is still under open items and is not cleared, Is there any more steps which I need to perform?
Thanks in advance.
Hi everyone,
thanks for all the replies. Points have been awarded
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I am trying to design the downpayment for my company and I am facing a critical technical issue that I would appreciate your help. The downpayments are treated as a full payment or advance payment .
The process which is the standard sap process
create PO > create request F-47> payment run F110> GR Migo > Miro or ERS > F-54 > F.13 auto clearing program.
Now the problem i am facing is similar to what some are facing in the post above. I understand that SAP dose not know what invoices to be applied to in F-54 and that is why we have to do it . However the problem is when I am processing multiple GR which will also creates multiple invoices yet for the same line item in the po, which was advanced paid. The problem the system in F-54 will clear the entire downpayment posted for this line item, yet the invoice is only a partial or that downpayment and i am expecting more invoices later. an average of 5 GRs per week , making 5 invoices per week for the same line item. is there way in sap to work around f-54 to allow multiple invoices to be cleared against the downpayment . I did find one solution in F-54 which is to enter the amount to be cleared with the invoice, but i have to do that manually and calculate the amount manually, and i don't want it to have any manual touch points. Please help ! thanks
u have done 80% of down oayment clearing..
In F-54 sceen u will transfer special GL (Down payment)to normai GL. after that u will go to F-44 screen clear that invoice with down payment... then invoice will be caleared..
follow above procedure.. and check in FBL1N ..
Reagards
Ranjith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Also u need to try F-44 for vendor clear
F-54 only clears the down payment and any excess TDS
Thanks and Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.