Skip to Content
0
Former Member
Jul 22, 2008 at 01:29 AM

how to make the date of activity is the same as the dateof assigned WBS?

23 Views

now the project is below:

1st layer: t-20090

2nd layer: t-20090.1

3rd layer: t-20090.1.1

3rd layer: t-20090.1.2

3rd layer: t-20090.1.1

network A

activity s001

activity s002

activity s003

3rd t-20090.1.2

network B

activity s101

activity s102

activity s103

all of the date of the activity is the same as the basic date of the assigned WBS.

now the user only move the activitys001 from t-20090.1.1 to t-20090.1.2

network A is also assigned to t-20090.1.1

now how to customize to make the activity s001'date is the same as the basic date of the WBS t-20090.1.2.

Please explain me all the steps to be required.

Thanks in advance!