Dear all,

I want to implement following:

It exist a change request and the CR-Manager has approved it. Also a subsequent document as a copy of the CR exist (e.g. Normal Correction). Now, the CR-Manager change the priority in the CR-Document. In case of this, the priority of the subsequent document should also updated.

Know my questions:

- is the BADI ORDER_SAVE the right one?

- which method should I use? (CHANGE_BEFORE_UPDATE, PREPARE, CHECK_BEFORE_SAVE)

- Any experiences in using the BADI ORDER_SAVE_CHARM?

Best regards