HI friends,
i am facing some problem in activity and yied quantity not displaying in CO11n.(i.e) actual data in comfirmation are not displayed. And in production order activity planned cost are not displyed and i am getting material cost only.
i have 3 activity setup, labour and machine. in co11n confirmation only setup activity quantity in min is displayes and yield qty, machine and labour activity qty are not displyed. when i enter any qty in yield i am getting an warning message "Total confirmation quantity not equal to planned confirmation quantity". only yield unit and activitys unit are displaye upart from set up activity qty
work centre settings give :
in capacity view capacity catagery 001 and 002 are maintained with processing formula SAP006 and SAP007 respectively. no other formula are given. in sheduling view processing formula SAP002 and teardown formula SAP003 are given. in costing view cost centre, activity and unit, reference indicator is checked and in formula SAP002 and SAP003 are given for machine and laboure activity respectively
i routing i have mentioned the duration of each activities
please give solution
with regards
arun kumar r v