Re : Backward Scheduling

Hi

How to set transit time, Picking time, Packing time for the required delivery date in Backward Scheduling Process.

Thanks

Mani

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jul 21, 2008 at 06:48 AM

    Hi

    The transit time is specified in the Route and the Pick/Pack times can be specified in Shipping point.

    Thanks,

    Ravi

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 21, 2008 at 06:53 AM

    Dear Mani,

    Example of Backward Scheduling for In-House Production

    Example Data

    Requirements date

    25.6. (Friday)

    Goods receipt processing time

    2 days (workdays)

    In-house production time for the material:

    6 days (workdays)

    Opening period

    6 days (workdays)

    Workdays = Monday to Friday, no bank holiday

    Scheduling

    Requirements data minus goods receipt processing time = order finish date

    25.6. (Friday) minus 2 workdays = 23.6. (Wednesday)

    Order finish date minus in-house production time = order start date

    23.6. (Wednesday) minus 6 workdays = 15.6. (Tuesday)

    Order start date minus opening period = order opening date

    15.6. (Tuesday) minus 6 workdays = 7.6. (Monday)

    Example of Backward Scheduling for External Procurement

    Example Data

    Requirements date

    31.10. (Monday)

    Planned delivery time of the material

    10 days (calendar days)

    Processing time for purchasing

    1 day (workdays)

    Goods receipt processing time

    2 days (workdays)

    Opening period

    10 days (workdays)

    Workdays = Monday to Friday

    Scheduling

    Requirements data minus goods receipt processing time = order finish date (provision date for vendor)

    31.10. (Tuesday) minus 2 workdays = 27.10. (Friday)

    Order finish date minus planned delivery time minus processing time for purchasing = release date for purchase requisition or order start date of planned order for external procurement.

    27.10. (Friday) minus 10 calendar days minus 1 workday = 16.10. (Monday)

    Release date minus opening period for planned order = opening date of planned order

    16.10. (Monday) minus 10 workdays = 2.10. (Monday)

    I hope it will help you,

    Regards,

    Murali.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Please follow this menu.

      SPRO-IMG-Sales and distribution-Basic function- Delivery scheduling and Transportation Planning.

      Thanks,

      Vrajesh