Skip to Content
avatar image
Former Member

Reg:BOM

Dear All,

When im trying to copy a BOM item from one plant to the other.

im not able to save it as the save button is in grey mode.

points assured for suitable ans.

Thanks & Regards,

Raj

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Jul 21, 2008 at 06:32 AM

    Dear Raj

    Are you trying in MM01 ?? If not, go to MM01, input the material code in the field Material and maintain the same material under under the tab "Copy from". Select the appropriate views and execute.

    thanks

    G. Lakshmipatih

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi ,

      1.Please extend the materials for the other plants

      2. once after extending it please use CS01 to create bom

      Thanks

      Kuntla

  • avatar image
    Former Member
    Jul 21, 2008 at 06:40 AM

    Dear Raj,

    Please go to MM01 trasaction enter thematerial no from which material you are going to copy in copy from material field.

    Enter the same material in Materials filed then click on select views select the views then enter the plant data (which you are goint to maintain BOM item) then maintain the all data in the selected views then save now system will save the changes.

    I hope it will help you,

    Regards,

    Murali.

    Add comment
    10|10000 characters needed characters exceeded