Former Member
Jul 19, 2008 at 11:49 AM

cbp

34 Views

we are using consumption based planning with MRP type VB. WE have maintained Reorder level and maintained lot-size as EX in material master

In case of reservations created for 201 movement, the reservation qty is not taken as required quantity in MRP run. But if reservations are created from project system module with account assignment "Q", MRP run is considering this qty also for planning.

Is this sap standard functionality ?

if we do not want this reservation to be included in CBP how to do that?

any suggestions