Dear All,
I have one strange scenario in my production system ,
There are purchase requisitions which are generated as a result of MRP run.
These requisitions are converted in Purchase Order. It is displayed in the PO
Now when I try to open the Requisitions the system says " Purchase Requisitions does not exists."
I understand that even if the PR is deleted it is shown in the system as deleted PR and it does not vanishes from the system.
Also if we say that when MRP is re-run the old PRs are overwritten, it is only for the PR which are untouched. In this case the PRs are converted into PO.
I tried to simulate the scenario in the development client but not possible.
Does any body came across such a scenario?
If so please help me.
With Best Regards
Yogesh C.