Hi Experts,
I have configured PO release strategy and have given 10% tolerance to PO value.
When I change PO value (more than 10%) after releasing the PO, but before taking Print out of PO, the system triggers new release strategy.
But when I change the PO value (More than 10%) after taking PO print out, system do not trigger the new release strategy.
I want the system to trigger new release strategy after PO print out (if its going beyond the tolerance).
Please help.
regards,
Anand