on 07-18-2008 10:40 AM
now the project is below:
1st t-20090
2nd t-20090.1
3rd t-20090.1.1
network A
activity s001
activity s002
activity s003
3rd t-20090.1.2
network B
activity s101
activity s102
activity s103
now the user move the activitys001 from t-20090.1.1 to t-20090.1.2
network A is also assigned to t-20090.1.1
only s001 assigned to t-20090.1.2
now how to customize to make the activity s001'date is the same as the date of the WBS t-20090.1.2.
Please explain me all the steps to be required.
Thanks in advance!
Hi,
In SPRO>
Project systems>dates> Dates planning in WBS>Define parameter for WBS Scheduling, tick adjust basic dates and also select the option WBS Determines the date or network determines the date based on your requirement.
Regards
N.Raju
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.