cancel
Showing results for 
Search instead for 
Did you mean: 

how to make the date of activity is the same as the assigned WBS'date?

Former Member
0 Kudos

now the project is below:

1st t-20090

2nd t-20090.1

3rd t-20090.1.1

network A

activity s001

activity s002

activity s003

3rd t-20090.1.2

network B

activity s101

activity s102

activity s103

now the user move the activitys001 from t-20090.1.1 to t-20090.1.2

network A is also assigned to t-20090.1.1

only s001 assigned to t-20090.1.2

now how to customize to make the activity s001'date is the same as the date of the WBS t-20090.1.2.

Please explain me all the steps to be required.

Thanks in advance!

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

In SPRO>

Project systems>dates> Dates planning in WBS>Define parameter for WBS Scheduling, tick adjust basic dates and also select the option WBS Determines the date or network determines the date based on your requirement.

Regards

N.Raju