FG start date not dependent on SFG finish date

348 Views

the planned order for the SFG has finish dates of 10/14/2008. however, its parent material, the FG, ends on 10/02/2008, 12 days before the SFG's finish. isnt the system supposed to schedule the SFG first, before the FG?