Hi guys,

My client has the following requirement. He has three plants say A,B & C. during mrp run purchase requisition is created for a material X for all the 3 plants. Now the client requirement is during auto po using ME59n all the pr created for the material x for plants A,B ,C need to be converted into one PO line item with the procurement plant as C as plant C is going to procure for all the 3 plants.

for e.g. during MRP run following PR are created

1 pr for material X for plant A with qty 10.

1 pr for material X for plant B with qty 20.

1 pr for material X for plant C with qty 30.

the requirement is during ME59n one PO is to created with a single line item with qty as 60 ( adding qty of all the 3 pr) with plant as C.

how to do this.

please help me guys.

Ram Kumar.