Jul 17, 2008 at 06:37 AM

Mrp scheduling

43 Views

Hai pp gurus

Two questions

1.I created one child material with both procurement type , plnd delivery time 2 days and gr processing time 5 days .During mrp its considered only gr processing time for plnd order . It not considered plnd delivery time ,. why ?

2.Already i configured backward scheduling for plant in opu3. created requirement for header material say as example 17.07.2008 50 qty

for child material given gr processing time 10 days .so during mrp it created planned order for child material 27.07.2008 .Actualy backward scheduling .