on 02-28-2018 12:09 PM
I create a routine to a material X by CA01 with sequence 0 (standard) ex: 005,10,20,25,30,40,0050,55,60,70,80,90, 100 etc... and with a sequence alternative 1 that have a start operation (branch) 0040, return operation 0090 and operation 0040, 0049, 0050,0051, 0055. 0060, 0070, 0080, 0090.
When I am creating a production order the system shows up me the pop up to select (YES) or (NO) the sequence alternative. What happen if I select NO. What operations are considered to the order? how about alternative sequence ?
Best Regards