Transportation calendar

Former Member
0 Kudos

We have a vendor V and location L setup in a transportation lane for product P. In mean of transport, we defined a time stream id as transportation calendar. The time stream id has only Monday in it.

Now my problem is that we are getting orders that other than Monday.

Is there a setting somewhere that overwrites the time stream id?

There is also no calendar setup in vendor master.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Solved.

Former Member
0 Kudos

Solved. The product at source location was not assigned to Model 000.

Edited by: Raj G on Jul 31, 2008 12:35 PM

Former Member
0 Kudos

did you try setting up a shiping calendar at the source and/or a receiving calendar at the customer location in APO with the same time stream (in /sapapo/loc3)?

Former Member
0 Kudos

Hi,

Thanks for the reply. We don't have any setup in vendor or receiving location. The reason being there are products that need to be delivered only on Mondays and also products that need to be delivered on other days as well. So we defined a Transportation lane with these materials and in the means of transport, we assigned the time stream id in transportation calendar.

Strangely, there are about 10 materials in that transportation lane. Only for few materials, the Purchase requisitions and POs are being created on days other than Mondays. I can see that in the product view RRP3. The rest of them are good.

I am wondering why this is happening.

Former Member
0 Kudos

Are your lead times for these products the same

Are you using the same means of transport for all of them??

Former Member
0 Kudos

The means of transport are same- Truck in Transportation lane. Where do I check the lead times?

How does the lead time change planning order dates?