on 07-16-2008 10:10 PM
We have a vendor V and location L setup in a transportation lane for product P. In mean of transport, we defined a time stream id as transportation calendar. The time stream id has only Monday in it.
Now my problem is that we are getting orders that other than Monday.
Is there a setting somewhere that overwrites the time stream id?
There is also no calendar setup in vendor master.
Solved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Solved. The product at source location was not assigned to Model 000.
Edited by: Raj G on Jul 31, 2008 12:35 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
did you try setting up a shiping calendar at the source and/or a receiving calendar at the customer location in APO with the same time stream (in /sapapo/loc3)?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for the reply. We don't have any setup in vendor or receiving location. The reason being there are products that need to be delivered only on Mondays and also products that need to be delivered on other days as well. So we defined a Transportation lane with these materials and in the means of transport, we assigned the time stream id in transportation calendar.
Strangely, there are about 10 materials in that transportation lane. Only for few materials, the Purchase requisitions and POs are being created on days other than Mondays. I can see that in the product view RRP3. The rest of them are good.
I am wondering why this is happening.