Hi All,
I would like to know about the number ranges for Cost Planning ,Revenue Planning & Budgeting.
As per Standard SAP,They have assigned some number ranges to budgeting (for CJ30 the no.range.no is "02" & for Investment Budgeting IM32 it is "10" ).
My queries:
1.Do we have number range for Cost planning & Revenue planning.i mean if we do CJR2 transaction,can we get a document no?
2. If i want to add a new number range for Budgeting ,how can i go ahead?
I checked with t-code OK11,here i can add a new Number Range,but how to assign the number range to Budgeting business transaction?
Kindly post your comments on this.
Thanks in Advance
Suresh
Apart from what you've mentioned, the following number ranges are defined in the standard system:
01 Project budget
02 Project plan
03 Order plan
04 Order budget
You usually (only) create the number range intervals as required.
Budget documents are generated automatically and this is standard. But if you need to write planning documents (which doesn't get generated automatically) you can set the business transaction 'Write Plan Items' using the user status on the WBS elements. Now if you plan/save against such WBS using CJR2, planning documents will be created.
If you've activated the integrated planning indicator for the WBS elements and do integrated planning along with cost centre (which is completely different process) planning document are automatically written, no need for user status here.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.