System not created any procurement proposal even requrment exists

65 Views

HI PP Gurus,

Scenario is A,B,C are the header material and D is the component material for them. Current stock of material D is 100 nos. Requirements of A, B, C for the month July is 80 nos. But for the next month means August requirement of header materials are 300 nos, but system has not created the planned order or purchase requisition for the material D.

My question is that for fulfilling the requirement of header materials, D material was available in the month of July. But still header requirement is in next month then why system has not create any procurement proposal for the D material. For this time I have suggested to create a manual PO but for the next time user wants to get procurement proposal directly from SAP. Can anybody tell the solution

Thanks in Advance