Hi,

After the Cproject ( PPM) is transfer to PPM, the status of project in PPM is set to Set to 'Flag for transfer'. If user decided to add any more activities after that and save it, the project is directly getting transferred to PS. How can we avoid this? I am looking for BADI on Change status so we can force the user to save it..

Also we have BADI 'GCC_PS_PROJECT_LABEL' method GET_WBS_ELEMENT. In this BADI based on task left right combination we derive our own WBS coding mask. When the user save the project ( after transfer has been done), we observed that task is not saved in DPR table at that time.. This is causing our BADI to fail..

How to force user/SAP to save the task first and then do the transfer..!! Any help is appreciated..

Regards

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Mar 14 at 06:29 PM

    Please advice, if anyone has got this situation..!!

    Thanks!

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 15 at 03:36 PM

    Dear Harish,

    It´s possible to define the "Transfer Type" in customizing under: spro > SAP Portfolio and Project Management > Project Management > Connection to External Systems > Accounting Integration > Activate Integration

    Here you can select "Automatic as of release of Project". Then the transfer is started when the project is receiving status "released".


    Maybe BAdI DPR_ATTRIBUTES (or DPR_EVENTS) can also be used to force the saving process of the user.

    Best regards,
    Judith