Hi gurus,

I'm working in SRM 5.0, ECS, backend ECC 6.0 (only one backend).

Everytime a SC is being approved a SRM PO has be created. Then a copy of this PO has to be created in ECC with document Type ATT and the same number of the SRM PO.

I have two questions

First of all I need to know the settings to make in 'Define objects in backend system' (for every purchasing Group and every Category ID, I need to create always PO in backend).

P.Gr Category ID Source System Internal proc. External proc.

  • * TRDCLNT011 Always external procurement PO if item data complete, otherwise P.Req.

Is this correct?

Secondly I need to understand the logic for number range definition

SRM Activities

1 - Define number range for Shopping Cart

I Need to create a SC number range

01 1000000000 - 1999999999

and then associate this range (01) to SHC transaction type ('Int.n' field)

2 - Define a number range for local PO

LO 7000000000 - 7999999999

and then associate this range (LO) to ECPO transaction type ('Int.n' field)

3- Create a new transaction type 'ATT' (backend PO)

4 - Define a number range for backend PO

PO 7000000000 - 7999999999

and then associate this range (PO) to ATT transaction type ('Int.n' field)

ECC Activities

1 - Define a number range for document type ATT

XX 7000000000 - 7999999999

and then associate this range (XX) to ATT Document type 'External

Is this correct?

I'd really appreciate your help

Points will be rewarded

Thaks in advance

Best regards

Gg

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

I dont think u need XX... Just put PO there.....

Former Member
0 Kudos

Hi. It all sounds about right.

I don't think the define backend docs does a great deal in ECS, you always get a PO with extended classic. If you ever want anything but a PO, a reservation for example, you have to not use extended classic for those items.

The number ranges look OK, although I think you only need 1 number range for the backend/local POs, it should all go in line on its own. It's been a while since I got an ECS system going so it is hard to remember.

The thing to do is try it in a test system and see what happens.

If anything goes wrong let us know on SDN what error messages you get and we should be able to help.