We copied simulation version XXX from 000 for financial planning simulation
We have a situation where we created the new version XXX from 000 5 days back.
And when a new material is CIFed from R/3 to active version (I would imagine by default it CIFs to Active version) only today.
I performed consistency checks for XXX verison and now without extending the Loc Product to the XXX verison, the material can be acessed through Interactive planning and Product View.
I Could also see that in the Product master, when i select Loc Product for that XXX version, It shows that the material is not assigned to the Version(Which is correct).
Could anyone please suggest why this is happening......
Why am I able to access the Loc Prod with the XXX version in Interactive planning and Product View even when I didnot assign the Loc Prod to XXX version.
Any hint is greatly rewarded.
Thank you in anticipation.