Hi

I have set up lot size procedure 1 in produc location and define subperiod of supply but the result is different than the one in the help documentation.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Matheus Korndoerfer
Feb 26 at 08:39 PM
0

Hello Carlos,

Are you running Heuristic or Optimizer? Please also provide a screenshot of its parameters.

Best regards,
Matheus

Show 2 Share
10 |10000 characters needed characters left characters exceeded

I am running Heuristic

captura.png (27.3 kB)
0

Hi Carlos,

Thank you for the information!

I'm not sure about this behavior as the approach of the static variant of periods of supply is, for each period to build up a projected inventory which covers the (dependent and independent) demand of n subsequent periods where n is derived of input key figure SUBPERIODSOFSUPPLY.

Please create an incident for component SCM-IBP-SUP-ALG with relevant information (i.e. System ID, Planning Area, SCM operator and Product ID - Location ID combination) and you may request to assign it to me.

Best regards,
Matheus