iNFO RECORD

Former Member
0 Kudos

Hi expert,

i got error in inforecod,

in my inforecord, i gave a planned deliver time but it shows make an entry in all required field. it is our problem.

actually this planned delivery time where it is effect and what is the main criteria for this?

thanks

vani

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member335885
Active Contributor
0 Kudos

Hi,

Use this function to calculate and change the planned delivery time. Using the documents in the system, the system calculates the number of days between the order being placed with the vendor and actual goods receipt. You can also use the planned delivery times calculated by the system in the master data as the planned delivery time.

By using this function you can achieve more efficient goods procurement from your vendor and therefore avoid overstock and out-of-stock situations.

To calculate the planned delivery time, the system determines the number of days between the order being placed with the vendor and the actual goods receipt for a freely definable combination of vendor, plant, material, purchasing organization and vendor subrange

Thanks & Regards,

Kiran

Former Member
0 Kudos

Hi,

Planned Delivery Time:

Number of calendar days needed to obtain the material or service if it is procured externally.

i.e.Time taken by Vendor to supply the material

Use

The planned delivery time is needed for planning material requirements and for scheduling.

While running Material Requirement Planning, this much number of days are considered.

regards,

Chintan

Former Member
0 Kudos

Hi,

This is one imp.factor .

The Del.date eq PO creation date+planned del. days.

The vendor should know what is the apx.del.date: This is one of facotr for vendor rating.

regards