Skip to Content
0

Alternate BOM selection

Feb 23 at 06:58 AM

23

avatar image
Former Member

Dear PP Experts,

I am facing few issues regarding Alternate BOM selection, below are my questions:

1- If I have more than 1 Alternate BOM, how can i select one of them before MRP run (NOTE : MRP run is carried out daily)

2- How to select Alternate BOM during conversion of Planned Order to Production Order and also while collective conversion of Planned Order to Production Order.

Please do the needful.

Thanks in advance.

Regards,

Salahuddin Shaikh

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

avatar image
Former Member
Feb 23 at 12:34 PM
0

Hello Salahuddin,

Please check the following SAP Note:

2312572 - BOM selection logic in MRP

This Note explains how the BOM is determined in MRP.

Best regards,

Krisztina

Share
10 |10000 characters needed characters left characters exceeded