Dear All,
i have the next problem:
1.- I have a real time infocube where i'm writting Plan data via query
2.- I execute a Process Chain with these steps:
1.- Switch Realtime InfoCube to Load Mode
2.- Load Actual data
3.- Switch Realtime InfoCube to Plan Mode
Then, the Plan data disapears from my eyes!
Switching on to load mode ( Step 1 ) convert IP request from yellow to green status, but it doesn't seems to be enough. I NEED TO CHANGE MANUALLY THE REQUEST TO GREEN STATUS AGAIN.
Any idea?
There is a function to change the request status before executing my process chain?
Best Regards